We’ve informed the Prime Minister and the remaining part of the government delegation that 33 km of the gas pipeline section Negotino-Bitola have been welded, 52 km of the open route and property and legal issues have been solved for over 75 km. The project is being realized according to the envisaged dynamics and we’re making efforts to smooth out the dynamic plan this year - said Bajram Redzepi, executive director of NER.